1. Construction of a 35 kV power transmission line from the SS01-35/6 kV substation to the DKS-110/35/6 kV substation for the KMPO and BATEMAN booster compressor station (35 kV - 16.4 km);
2. Construction of external power supply of the UKS "Girsan-Chulkuvar" as part of the construction of a 2-circuit 35 kV overhead power line (35 kV - 26.5 km, 6 kV - 19.0 km);
3. Construction of a 110 kV power transmission line (20 km) and a 110/35/6 kV substation for power supply to UKS-1-11 at the Shurtan field (110 kV - 48.13 km, 35 kV - 21.3 km, 6 kV - 3 km);
4. Construction of a 110 kV power transmission line - 44 km and a 110/35/6 kV substation for external power supply of UKS-1-2 at the Samantepe field (110 kV - 44.4 km, 6 kV - 5 km);
5. Construction of overhead power lines from the Muynak 10 kV and 0.4 kV substation to 110/10 kV Aral to the 0.4 kV switchgear of the Sharkiy Berdak DCS facility (10 kV-17 km) .
The total length of construction of power transmission lines during this period is 200.73 km .
(16.4+ 26.5+ 19.0+48.13+21.3+3.0+44.4+ 5.0+17.0)