1. Construction of the Fergana-Rishtan gas pipeline, line II, diameter 720 mm, L-39 km (02.2022-07.2022);
2. Construction of the automated gas metering station (GMS) “Karakalpakia-2” (06.2023- 08.2023);
3. Construction of the automated GIS “BEYNEU” (08.2023-10.2023);
4. Construction of the Bukhara-Ural L-22 km main gas pipeline (07.2023-02.2024);
5. Major repairs of section 472-528 km of the II line of the Bukhara-Ural L-56 km main gas pipeline (09.2023-02.2024);
6. Installation of a high-pressure steam pipeline, a low-pressure steam condensate pipeline and a ROU from Uzbekistan GTL LLC to ShGHK LLC;
7. Construction of the second line of the Shurtan-Sherabad gas pipeline, 161 km long, and a compressor station with a capacity of 32 MW (under construction);